Government Center

Completed

 

ITB 2021-08 NW 82 Street and NW 114 Avenue Traffic Signal

  • Project Scope: Four – Way Traffic Signal and pedestrian signals at the intersection of NW 82nd Street and 114th Avenue.  Project also includes milling & resurfacing, stripping, and new curbing.
  • Estimated Completion Date: August 2022
  • Start Date:  January 2022
  • % Complete: 100%
  • Contractor: A.U.M. Construction, Inc.
  • Duration: 180 Calendar Days
  • Cost: $406,305.90


Stormwater Improvement Project AT NW 89 Place and NW 24 Terrace

  • Project Scope: Stormwater improvements along NW 89 Place from NW 25 Street to NW 23 Street and along NW 24 Terrace between NW 89 Place and NW 25 Street.  Project also includes Milling & Resurfacing & Stripping.
  • Estimated Completion Date: July 2022
  • Start Date: February 2022
  • % Complete: 100%
  • Contractor: ADA Engineering Inc.
  • Duration: 150 Calendar Days
  • Cost: $461,156.00

Current Projects


ITB 2022-23: Stormwater Improvement Project at Sub Basin NW 33 ST W

  • Project Scope: Stormwater improvements along NW 33 Street between NW 87th Avenue and NW 82nd Avenue. Project also includes Milling & Resurfacing & Striping.
  • Estimated Completion Date: April 3, 2023
  • Start Date:  December 5, 2022
  • % Complete: 0%
  • Contractor: Metro Express Inc.
  • Duration: 120 Calendar Days
  • Cost: $550,180.40
  •  Construction Notice - Sub Basin NW 33 ST W


ITB 2022-22 NW 58th Street Outfall

  • Project Scope: Stormwater improvements along NW 57th Street between NW 79th Avenue and NW 78th Avenue and along NW 79th Avenue and NW 58th Street. A 48” Outfall will be constructed along the NW 58th Street canal to discharge near the intersection of NW 79th Avenue and NW 58th Street.  Project also includes Milling & Resurfacing & Stripping.
  • Estimated Completion Date: May 12, 2023
  • Start Date:  November 14, 2022
  • % Complete: 0%
  • Contractor: ADA Engineering Inc.
  • Duration: 180 Calendar Days
  • Cost: $1,576,841.44
  •  Construction Notice - NW 58 Street Outfall
  • CDBG-MIT Requirements: Please refer to the Civil Rights Compliance regulations for the Fair Housing, Equal Employment Opportunity (EEO), and Section 504 and the Americans with Disabilities Act (ADA) as it relates to grant funding. For additional question and/or concerns as it relates to CDBG-MIT grant requirements please contact Stephanie Bortz, Stormwater Utility Manager at  Stephanie.Bortz@cityofdoral.com or  305-593-6740 ext. 6024.
    • Office of Housing Advocacy of Fair Housing Coordinator
       (786) 469-4545
       housingadvocacy@miamidade.gov
       701 NW 1st Court
      Miami, FL 33136
       
    • Miami District Office of EEO Coordination
       1-800-669-4000
       305-808-1758
       100 SE 2nd Street
      Suite 1500
      Miami, FL 33131
       
    • Miami-Dade Office of ADA Coordination
       305-375-5893
       305-375-5753
       111 NW 1st Street
      24th Floor
      Miami, FL 33128


ITB 2022-03 Intersection Improvements at NW 114 Ave & NW 112 Ave on NW 58 St.

  • Project Scope: Intersection Improvements at NW 114 Ave./58 St. and NW 112 Ave./58 St.
  • Estimated Completion Date: November 2022
  • Start Date:  June 20, 2022
  • % Complete: 25%
  • Contractor: H & R Paving
  • Duration: 150 Calendar Days
  • Cost: $296,231.70


ITB 2022-05 Doral Boulevard Median Landscaping Improvements

  • Project Scope: Median Landscape Improvements from NW 97th Avenue to Palmetto Expressway
  • Estimated Completion Date: December 2022
  • Start Date: July 25, 2022
  • % Complete: 30%
  • Contractor: Superior Landscaping and Lawn Service, Inc.
  • Duration: 150 Calendar Days
  • Cost: $2,075,404.68

Upcoming Projects

  • ITB 2021-10 Citywide Sidewalk Improvements Phase II
  • ITB 2022-03 Intersection Improvements at NW 114 Ave./58 St. and NW 112 Ave./58 St.
  • ITB 2022-xx - Doral Boulevard Median Landscaping Improvements