Canal Bank Stabilization Project

Project: Canal Bank Stabilization Program – Year 5B
Description:  Canal bank stabilization through geo-web techniques of the Dressels Canal along Doral Blvd. Between NW 97 Avenue and NW 87 Avenue. Project also includes the construction of a maintenance/pedestrian/bike shared use path along the north side of the Dressels Canal between NW 97 Ave. and NW 87 Ave.
Cost: $3,197,441.20
Schedule: Anticipated Completion Date – October 2019
Contractor: ENCO LLC

Canal Bank Stabilization Project

Project: Canal Bank Stabilization Program – Year 7
Description:  Canal bank stabilization through geo-web techniques along the north side of the Dressels Canal between NW 97 Ave. and NW 102 Ave and the Northline Canal between NW 97 Ave. and NW 87 Ave. along NW 25 St.
Cost: Pending Award
Schedule: Project to be awarded during November 2019 Council Meeting
Contractor: Pending Award

Stormwater Improvement Projects

Project: Stormwater Improvements at NW 21 Street
Description:  Stormwater Improvements include adding linear feet of exfiltration trench (French Drain), adding manhole stormwater structures, and connecting the system to the existing infrastructure along NW 21 St. between NW 84 Ave. and NW 82 Ave.  
Cost: $168,769.10
Schedule: Anticipated Start Date- October 21, 2019 (60 Calendar Day)
Contractor: Maggolc, Inc.


Project: Stormwater Improvements at Sub Basin A-4
Description:  Stormwater Improvements include adding linear feet of exfiltration trench (French Drain), adding stormwater structures (catch basin and manhole), and connecting the system to the existing infrastructure along NW 84 Ave. between NW 25 St. and NW 12 St.
Cost: $798,280.00
Schedule: Anticipated Start Date - January 2020 (240 Calendar Day)
Contractor: Maggolc, Inc.