Road Improvements Construction Update
25st-project
Nightly Closure of Eastbound NW 25 Street

All eastbound travel lanes on NW 25 Street will be closed at NW 79 Avenue from Tuesday, August 25 through Friday, August 28 between the hours of 9 p.m. to 5:30 a.m.

Eastbound driver on NW 25 Street can:

  • Go north on NW 79 Avenue
  • East on NW 36 Street
  • South on NW 72 Avenue/Milam Dairy Road to connect with NW 25 Street

The closures will allow the contractor to place bridge beams over the roadway. Please note that this schedule may change due to bad weather or other unforeseen conditions.

For more information about the NW 25 Street Construction Project, please contact Construction Public Information Specialist Oscar Gonzalez at 786-280-0983 or Project Engineer Nelson Perez at 305-216-5112 or go to www.fdotmiamidade.com.

Drivers are encouraged to call 511 before they drive or log on to www.fl511.com to get real-time traffic and lane closure information. FDOT reminds drivers that wearing a safety belt is the single most effective way to protect people and reduce fatalities in motor vehicle crashes. Please drive cautiously in work zones.

connectingcommunities

Nighttime Closure of Eastbound State Road (SR) 836 Ramp to NW 72 Avenue/Milam Dairy Road

All eastbound travel lanes on NW 25 Street will be closed at NW 79 Avenue Friday, August 28 and Saturday, August 29 (Monday, August 31 is an alternate date) between the hours of 9 p.m. to 5:30 a.m.

Eastbound driver on NW 25 Street can:

  • Go north on NW 79 Avenue
  • East on NW 36 Street
  • South on NW 72 Avenue/Milam Dairy Road to connect with NW 25 Street

The closures will allow the contractor to place bridge beams over the roadway. Please note that this schedule may change due to bad weather or other unforeseen conditions.

For more information about the NW 25 Street Construction Project, please contact Construction Public Information Specialist Oscar Gonzalez at 786-280-0983 or Project Engineer Nelson Perez at 305-216-5112 or go to www.fdotmiamidade.com.

Drivers are encouraged to call 511 before they drive or log on to www.fl511.com to get real-time traffic and lane closure information. FDOT reminds drivers that wearing a safety belt is the single most effective way to protect people and reduce fatalities in motor vehicle crashes. Please drive cautiously in work zones.


Major Transportation Project by FDOT to Start in Doral

As part of the Florida Department of Transportation’s road and traffic improvements for our area, construction of the western portion of the NW 25th Street Viaduct (Elevated Bridge) project will start in June, 2012.

The purpose of the project is to conclude the viaduct (elevated bridge) that will direct truck traffic directly into Miami International Airport hence alleviating local traffic and improving the quality of life of Doral residents and visitors.

The work by FDOT will extend from SR 826 in the east to NW 89 Court in the west with adjoining improvements to NW 79 Ave, NW 82 Ave, NW 84 Ave and NW 87 Ave.

The massive project will be broken into five phases that will encompass the next four years. The first phase includes the following:

  • Phase 1A – Two months of night work to remove medians and landscaping on adjacent NW 79, 82, 84 and 87 Avenues to facilitate Maintenance of Traffic.
  • Phase 1B – 18 months of day and night work to enclose canal and build new lanes on the north side of NW 25 St. Traffic to remain on South side two lanes each direction but side streets may be narrowed to one lane each direction and majority of turn lanes will be removed.

Although Doral drivers will experience delays that will continue until 2016, every effort will be made to minimize impacts to traffic. Drivers using these streets are highly encouraged to use alternate routes such as NW 12 Street and NW 33 Street. It is also recommended to allow extra time when commuting to accommodate for traffic and other detours.


Download a project fact sheet from the Florida Department of Transportation.

Obtenga más información en Español sobre el proyecto del Departamento de Transportación del Estado de la Florida.

Visit the Miami-Dade Florida Department of Transportation website for additional project updates.


  • Join Our Mailing List
  • Trolley Information
  • Business Tax Receipt
  • Hurricane and Flood Information
  • Jobs Information
  • Hurricane Preparedness
  • CodeComplaint
  • Severe Weather Feed
  • EPermitting Information
  • 25stIcon826-836
  • Doral TV
  • Doral 311 Modal
  • Road Updates Doral
  • Decor District Information
  • Building Department
  • Code Red Information
  • Doral Dashboard
  • Doral Iphone App

City of Doral, Florida | 8401 NW 53rd Terrace, Doral, FL 33166 | 305-59DORAL (305-593-6725)
City of Doral Police Department | 6100 NW 99th Avenue, Doral, FL 33178

Mission Statement:
To serve our community by relentlessly pursuing the highest quality of life through the delivery of efficient, sustainable, transparent ethical and accountable government.

Link to our Privacy Policy
E-Mail Disclaimer: Under Florida law, e-mail addresses are public records. If you do not want your e-mail address released in response to a public records request, do not send electronic mail to this entity. Instead, contact the City by phone or in writing.